SR 91 & Norton Road Improvement Project

SR 91 Norton New Lane Shift

Construction Progress


Work continues on the widening project at the Norton Road/SR 91 intersection improvement at the Stow-Hudson border.  Crews are widening on the south side of Norton Road, west of SR 91. Mid-June, once all of the new curb and pavement has been replaced on the southerly section of the roadway, the contractor will begin work on the north side of Norton Road in this area. New traffic patterns, lane shifts and minor delays can be expected, but two-way traffic will be maintained.

The bridge on SR 91/Darrow Road over the bike trail has been replaced with an arch culvert. The bike trail between Sowul Boulevard and Norton Road is open. The trail surface is compacted limestone. Additional work such as sealing, painting, and grouting the culvert along with placing the asphalt base and surface will take place when it is warmer in late spring and summer, at which time the trail will be closed. Please view the Summit County Metro Parks website for bike trail updates and alternative routes.

Darrow Road now has two lanes, northbound and southbound, and a left turn lane for southbound traffic at Fishcreek Road. Fishcreek Road has been reconstructed with new curbs and a future turn lane to southbound Darrow Road.  The contractor is now working on replacing the existing traffic signals at SR 91/Norton Road and installing a new traffic signal at SR 91/Fishcreek Road. The signal work will continue into the spring.  Once operational, the temporary signal at the Shoppes of Stow and Bruegger’s Bagels will be removed.

All underground utility work has been completed for the Norton Road portion of the project. Crews will now begin the necessary work to construct the shared use path and widening work on Norton Road. Two-way traffic will continue while this work takes place through the summer. Note that lane shifts and changes in the traffic patterns will occur while the work progresses.

Final paving is scheduled for July with landscaping and clean-up scheduled for August, 2017.


Documents


Related documents for this project can be viewed by clicking here: SR 91 & Norton Road Improvement Project.

Update


  • The new traffic signal at SR 91 and Norton Road is now operational.
  • Crews are now widening on the south side of Norton Road, west of SR 91.
  • Work will begin on the north side of Norton Road in mid-June.
  • The bike trail is currently open, however, closure will be necessary in late Spring and Summer.

Maintenance of Traffic

 
During construction, temporary lane closures will be required, but access shall be maintained to all residences and commercial establishments.

Two-way traffic will be maintained throughout the project.

Contact Information


The City of Stow Engineering Department is the lead agency.

If you have questions regarding this project, please call 
330-689-2719 or email Jim McCleary here

Click below for an Ohio.com article:

SR 91 Norton Ohio.com Image

Project Description


The intersection at SR 91 and Norton Road experiences substantial traffic delays and congestion, especially during rush hour traffic. This project will reduce the delays experienced by travelers.

Improvements in Hudson and Stow in the SR 91 (Darrow Road) and Norton Road area continue.  These improvements will better accommodate vehicles, bicycles and pedestrians on Norton Road. This work includes adding right-turn-only lanes and resurfacing on both SR 91 and Norton Road. In addition, the project will include upgraded signalization of the intersection, a shared-use path on Norton Road, plus new curbs, walks, signing, pavement markings, and drainage improvements to SR 91.