N. Main Street Improvement Project

Support Stores

Stay Connected

Construction Update:


There are a few contract items that still need complete, those follow:

  • Finish final striping (potential night work)
  • Finish mid-block cross walk (no impact to traffic)
  • Finish installing traffic signs (no impact to traffic) –
  • Pour inverts (traffic shifts maintaining 2 lanes/potential night work)
  • Video storm sewer (traffic shifts maintaining 2 lanes/potential night work)
  • Finish railing and miscellaneous step work (no impact to traffic)
  • Finish miscellaneous signal items (no impact to traffic)
  • Finish existing paver palletizing (no impact to traffic)

The contractor has a couple items noted above that they have lead times which may take through October.

There are also miscellaneous “punchlist” items that should be complete over the next 30-60 days.


Project Questions?

Contact our Engineering Department:
  • By phone at (330) 342-1770.
  • By Email.
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7

Project History



The North Main Street Improvement Project between SR 303 and Owen Brown Street includes infrastructure improvements and a fresh new look, including new lighting and sidewalk/pedestrian areas, improved crosswalks, landscaping including street trees and planters. With the assistance of AMATS funding and an ODNR Grant, The Ohio Department of Transportation will resurface North Main Street as part of this project.

For more project details, visit our story map.
 

Pervious Pavers Ohio EPA Grant

As part of the N. Main Street Improvement Project, the City installed new pervious pavers with the assistance of an Ohio EPA Grant. The pervious pavers will aid in treating storm water runoff. To learn more, click here:

Click image to view construction area:

North Main Map darkened

Click image below to view a Story Map:

North Main Story Map Link Photo
  1. Frequently Asked Questions
  2. Length
  3. Scope
  4. Driving
  5. Stores
  6. Parking
  7. Sandstone
  8. Updates
  9. Events
  10. Contact

How long will the project last? 
The project began in 2016 with estimated completion fall of 2017.

What is the scope of the project?

  • Full pavement replacement
  • New overhead crosswalk signals and improved crosswalk designs
  • New textured sidewalk and pavers
  • New light design
  • Diagonal parking
  • Street trees, benches, planters, landscaping
Will my drive to work be impacted?
Some work will be done at night, with possible periodic lane closures after 8 p.m.  During the day, traffic will be maintained, but the lanes will shift for construction which may cause traffic delays. Truck detours will begin during Phase 2. The best way to stay informed is to sign up for our Road Construction Updates and receive email/text messages about lane shifts or closures and other issues that might arise during construction.

Will I be able to visit my favorite North Main Street store?
Yes! Sidewalk access to the stores and businesses will be maintained at all times.  

Will parking in front of the North Main Street stores be available?

While the diagonal parking areas in front of some of the stores may be closed for a period of time, access to all other public parking areas will remain open. 

What will happen to the sandstone sidewalks and curbs?
The approximately 20 square feet of sandstone sidewalk will be removed and stored for possible future use. The sandstone curb will be removed and replaced back into its place as part of the project. Curbing that is cracked or damaged will be removed.

Where's the best place to go to stay up to date on this project?
There are several ways to stay informed. 

  • Website. Check this website page for updates.
  • Story Map. Click on the visual story map at the top of this page that provides detail about the construction, timeline, features and more or click here.
  • Social Media.  For real-time updates on the construction and its impact on traffic, follow us on social media.
  • Road Construction Updates.  Sign up to receive our Road Construction updates for real time traffic alerts regarding this project.Sign up here.
  • Merchant Updates.  If you are a merchant, business, or property owner in the downtown area, sign up for weekly updates specific to how this project may impact your business.  To sign up, click here.
  • Visit HCTV.  
  • Visit the City's YouTube Channel.
What about the great events on the greens this summer? Will they continue?
Yes, the events on the green will be held as scheduled. For event information, visit our Community Calendar.

Who should I call or email if I have questions or concerns about the project?
Call our Engineering Department at 330-342-1770.
Email our Engineering Department at engineering@hudson.oh.us.