Barlow Road Widening

Where on Barlow Road?

  • SR 91 to Terex Road intersection.

How long?

  • Construction began 7/27/16.
  • Barlow Road is open 9/29/16.

What was done?

  • Resurfacing Barlow Road.
  • Widening 18 inches on both sides.
  • Storm crossing improvements.
The City of Hudson entered into a contract with Ronyak Paving Company to resurface Barlow Road from SR 91 to the Terex Road (West) intersection, excluding a 1,000 ft. section of roadway adjacent to the existing railroad crossing. 

For questions regarding this project please email: engineering@hudson.oh.us or call: (330) 342-1770 (Monday-Friday 7:30am-4:00pm, excluding holidays). 

Detour map that was in place during construction:

Barlow Rd Detour Map